The ArmorUltra Epoxy System is a high-performance, durable floor coating designed for industrial and commercial environments. For optimal results, follow these step-by-step installation instructions:

  1. Surface Preparation: Ensure the substrate is clean, dry, and free from oils, grease, or debris. Mechanical preparation such as grinding or shot blasting is recommended for best adhesion.
  2. Priming: Apply ArmorUltra primer to the prepared surface. This helps seal the substrate and enhances the bond between the floor and the epoxy coating. Allow the primer to dry according to the manufacturer’s instructions, typically 6–12 hours.
  3. Mixing the Epoxy: In a clean container, mix the ArmorUltra epoxy base and hardener according to the specified ratio. Use a mechanical mixer to ensure thorough blending for at least 2-3 minutes.
  4. Application: Pour the mixed epoxy onto the floor and spread it evenly using a roller or squeegee. Start from the farthest corner, working towards the exit. Apply the first coat uniformly, and allow it to cure (approximately 24 hours).
  5. Topcoat Application: After the base coat has cured, apply the ArmorUltra topcoat. This adds a protective layer that increases resistance to chemicals and abrasions.
  6. Curing: Allow the entire system to fully cure before exposing it to traffic, typically 48-72 hours.

Following these steps will ensure a long-lasting, professional-grade floor finish.